Documents:
0
Shipping:
$0.00
Tax:
$0.00
Total:
$0.00
A101 -1997, Standard Form of Agreement between Owner and Contractor-Stipulated Sum
$8.00 (minimum order of 5 copies)
A105 -1993, Standard Form of Agreement between Owner and Contractor for a Small Project and A205-1993, General Conditions of the Contractor for Construction of a Small Project
$8.00 per 2-document set
A107-1997, Abbreviated Standard Form of Agreement between Owner and Contractor for Construction Projects of Limited ScopeStipulated Sum
$8.00 each
A201-1997, General Conditions of the Contract for Construction
$10.00 (minimum order of 5 copies)
A305-1986, Contractor's Qualification Statement
$5.00 (minimum order of 5 copies)
B141-1997, Standard Form of Agreement Between Owner and Architect with Standard Form of Architect's Services
$8.00 (minimum order of 5 copies)
G701-2000/2001, Change Order
$18.00 50-pack
G702-1992, Application and Certificate for Payment and G703, Continuation Sheet
$18.00 50-pack or Continuous Roll
A101 -1997, Standard Form of Agreement between Owner and Contractor-Stipulated Sum
A101 is a standard form of agreement between owner and contractor for use where the basis of payment is a stipulated sum (fixed price). The document adopts by reference and is designed for use with A201-1997, General Conditions of the Contract for Construction. When used together, the documents are appropriate for most project types.
$8.00 (minimum order of 5 copies)
A101-1997, Standard Form of Agreement between Owner and Contractor-Stipulated Sum
A101 is a standard form of agreement between owner and contractor for use where the basis of payment is a stipulated sum (fixed price). The document adopts by reference and is designed for use with A201 -1997, General Conditions of the Contract for Construction. When used together, the documents are appropriate for most project types.
$8.00 (minimum order of 5 copies)
A105 -1993, Standard Form of Agreement between Owner and Contractor for a Small Project and A205-1993, General Conditions of the Contractor for Construction of a Small Project
A105 and A205 were developed for use where payment to the contractor is based on a stipulated sum (fixed price) and where the project is modest in size and brief in duration. Intended for use in conjunction with one another, the two documents are sold as a set and share common instructions. They are for use with AIA Document B155-1993, Standard Form of Agreement Between Owner and Architect for a Small Project. Although A105, A205 and B155 may share some similarities with other AIA documents, these Small Projects documents should NOT be used in tandem with other AIA document families without careful side-by-side comparison of contents.
$8.00 per 2-document set
A105-1993, Standard Form of Agreement between Owner and Contractor for a Small Project and A205-1993, General Conditions of the Contractor for Construction of a Small Project
A105 and A205 were developed for use where payment to the contractor is based on a stipulated sum (fixed price) and where the project is modest in size and brief in duration. Intended for use in conjunction with one another, the two documents are sold as a set and share common instructions. They are for use with AIA Document B155-1993, Standard Form of Agreement Between Owner and Architect for a Small Project. Although A105, A205 and B155 may share some similarities with other AIA documents, these Small Projects documents should NOT be used in tandem with other AIA document families without careful side-by-side comparison of contents.
$8.00 2-document set
A107-1997, Abbreviated Standard Form of Agreement between Owner and Contractor for Construction Projects of Limited ScopeStipulated Sum
A107 is for use where the basis of payment is a stipulated sum (fixed price), this document is appropriate for construction projects of limited scope not requiring the contractual complexity of A101-1997 and A201-1997 in combination. It may be used where the owner and contractor have established a prior working relationship (e.g., a previous project of like or similar nature), or where the project is relatively simple in detail or short in duration.
$8.00 each
A107-1997, Abbreviated Standard Form of Agreement between Owner and Contractor for Construction Projects of Limited ScopeStipulated Sum
A107 is for use where the basis of payment is a stipulated sum (fixed price), this document is appropriate for construction projects of limited scope not requiring the contractual complexity of A101-1997 and A201-1997 in combination. It may be used where the owner and contractor have established a prior working relationship (e.g., a previous project of like or similar nature), or where the project is relatively simple in detail or short in duration.
$8.00
A111-1997, Standard Form of Agreement between Owner and ContractorCost of the Work Plus a Fee, With a Negotiated Guaranteed Maximum Price (GMP)
A111 is appropriate for use on most projects requiring a negotiated guaranteed maximum price, when the basis of payment to the contractor is the cost of the work plus a fee. Adopts by reference and is intended for use with A201-1997.
$8.00
A114-2001, Standard Form of Agreement between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee without a Guaranteed Maximum Price (GMP)
Appropriate for use on projects where the basis of payment to the contractor is the cost of the work plus a fee, and the cost is not fully known at the commencement of the construction.
$8.00
A201/SC-1999, Federal Supplementary Conditions of the Contract for Construction
A201/SC is for use on certain federally assisted construction projects. A201/SC adapts A201 by providing (1) necessary modifications of the general conditions, (2) additional conditions and (3) insurance requirements for federally assisted construction projects.
$3.50
A201-1997, General Conditions of the Contract for Construction
A201 is an integral part of the contract for construction, setting forth the rights, responsibilities and relationships of the owner, contractor and architect. This document is typically adopted by reference into other AIA documents, such as Owner-Architect agreements, Owner-Contractor agreements and Contractor-Subcontractor agreements.
$10.00 (minimum order of 5 copies)
A305-1986, Contractor's Qualification Statement
An owner preparing to request bids or to award a contract for a construction project often requires a means of verifying the background, history, references and financial stability of any contractor being considered. The time frame for construction and the contractor's performance history, previous experience and financial stability are important factors for an owner to investigate. A305 provides a sworn, notarized statement with appropriate attachments to elaborate on important aspects of the contractor's qualifications.
$5.00 (minimum order of 5 copies)
A310-1970, Bid Bond
A310 is a one-page form that establishes the maximum penal amount that may be due to the owner if a selected bidder fails to execute the contract and provide any required performance and payment bonds.
$3.00 (minimum order of 5 copies)
A312-1984, Performance Bond and Payment Bond
This form incorporates two bonds covering first, the contractor's performance, and second, the contractor's obligations to pay Subcontractors and others for materials and labor. In addition, the A312 obligates the surety to act responsively to the owner's requests for discussions aimed at anticipating or preventing a contractor's default.
$5.00
A401-1997, Standard Form of Agreement between Contractor and Subcontractor
A401 is intended for use in establishing the contractual relationship between the contractor and subcontractor. It spells out the responsibilities of both parties and lists their respective obligations, which are written to parallel A201-1997. Blank spaces are provided where the parties can supplement the details of their agreement. A401 may be modified for use as a subcontractor-subsubcontractor agreement.
$8.00
A501-1995, Recommended Guide For Competitive Bidding Procedures and Contract Awards for Building Construction
A501 outlines appropriate procedures in the bidding and award of contracts when competitive lump sum bids are requested in connection with building and related construction.
$5.00
A521-1995, Uniform Location of Subject Matter
A521 is a tabulation to guide in determining the proper placement and phrasing of information customarily used on a construction project, the document shows the importance of maintaining uniformity in location and language from document to document with respect to subject matter. Inconsistencies in either area may cause confusion, delay or unanticipated legal problems.
$5.00
A701-1997, Instructions to Bidders
A701 is for use when competitive bids are to be solicited for construction of the project. Coordinated with A201-1997 and its related documents, A701 contains instructions on procedures to be followed by bidders in preparing and submitting their bids, including bonding. Specific instructions or special requirements, such as the amount and type of bonding, are to be attached as supplementary conditions.
$8.00 (minimum order of 5 copies)
B141-1997, Standard Form of Agreement Between Owner and Architect with Standard Form of Architect's Services
B141 is a flexible contracting package that allows architects to offer clients a broad range of services spanning the life of a project, from conception to completion and beyond. It is structured in a multi-part format consisting of a standard form of agreement containing initial information, terms and conditions, compensation, and a service form; and a standard form of architect's services: design and contract administration, which defines the architect's scope of services. The separation of the scope of services from the rest of the Owner-Architect agreement allows users the freedom to choose alternative scopes of services. The AIA intends to publish additional scopes of services that correlate to the terms and conditions of B141-1997 in the near future.
$8.00 (minimum order of 5 copies)
B151-1997, Abbreviated Standard Form of Agreement between Owner and Architect
B151 is an abbreviated standard form of agreement between owner and architect intended for use on construction projects of limited scope where the complexity and detail of AIA Document B141-1997 is not required, and where services are based on five phases: schematic design, design development, construction documents, bidding and negotiation, and construction. This document may be used with a variety of compensation methods, including percentage of construction cost, multiple of direct personnel expense, and stipulated sum. B151 is intended to be used in conjunction with A201-1997.
$8.00 (minimum order of 5 copies)
B155-1993, Standard Form of Agreement between Owner and Architect for a Small Project
B155 is a standard form of agreement between an owner and architect intended for use on a small project. B155 was developed for use with AIA Document A105, Standard Form of Agreement Between Owner and Contractor for a Small Project, and A205, General Conditions of the Contract for Construction of a Small Project. These documents are specifically coordinated for use as a set. Although A105, A205 and B155 may share some similarities with other AIA documents, the Small Project documents should NOT be used in tandem with other AIA document families without careful side-by-side comparison of contents.
$5.00
B163-1993, Standard Form of Agreement between Owner and Architect for Designated Services
B163 is the most comprehensive AIA Owner-Architect agreement. This three-part document contains, among other things, a thorough list of 83 possible services divided among nine phases, covering pre-design through supplemental services. Part One of the document deals with variables typical of many Owner-Architect agreements, such as compensation and scope of services. Part Two contains detailed descriptions of the specific services found in Part One's matrix. Part Three contains general descriptions of the parties' duties and responsibilities.
$9.00
B181-1994, Standard Form of Agreement between Owner and Architect for Housing Services
This document has been developed with the assistance of the U.S. Department of Housing and Urban Development (HUD) and other federal housing agencies, and is primarily intended for use in multi-unit housing design. B181 requires that the owner furnish cost-estimating services. B181 is coordinated with and adopts by reference A201-1997.
$5.00
B188-1996, Standard Form of Agreement Between Owner and Architect for Limited Architectural Services for Housing Projects
B188 is intended for use in situations where the architect will provide limited architectural services in connection with a development housing project. It anticipates that the owner will have extensive control over management of the project, acting in a capacity similar to that of a developer or speculative builder of a housing project. B188 is not coordinated for use with any other AIA standard form contract.
$9.00
B352-2000, Duties, Responsibilities and Limitations of Authority of the Architect's Project Representative
When and if the owner wants additional project representation at the construction site on a full- or part- time basis, B141-1997 and other AIA Owner-Architect agreements reference B352 to establish the project representative's duties, responsibilities and limitations of authority. The project representative is employed and supervised by the architect. B352 is coordinated for use with both B141-1997 and B163-1993, as well as A201-1997.
$3.00
B431-1993, Architect's Qualification Statement
B431 is a standardized outline of information that a client may wish to review prior to selecting an architect for a particular project. It may be used as part of a request for proposals (RFP) or as a final check on the credentials of an architect. Under some circumstances, B431 may also be attached to the Owner-Architect agreement to show, for example, the team of professionals and consultants expected to be employed on the owner's project.
$5.00
B727-1988, Standard Form of Agreement Between Owner and Architect for Special Services
B727 is the most flexible of the AIA Owner-Architect agreements, in that the description of services is left entirely up to the ingenuity of the parties. Otherwise, many of the terms and conditions are very similar to those found in B141-1997. B727 is often used for planning, feasibility studies and other services (such as construction administration), which do not follow the complete phasing sequence of services set forth in other AIA documents. If construction administration services are to be provided, care must be taken to coordinate B727 with the appropriate general conditions of the contract for construction.
$5.00
C141-1997, Standard Form of Agreement Between Architect and Consultant
Standard form of agreement between an architect and consultant, establishing their respective responsibilities and mutual rights. This document is most applicable to engineers, but may also be used by consultants in other disciplines providing services to architects. Its provisions are in accord with those of B141-1997, B141/CMa-1992, B151-1997 and B163-1993.
$8.00
C142-1997, Abbreviated Standard Form of Agreement between Architect and Consultant
Abbreviated form of agreement between an architect and consultant. This document adopts the terms of a prime agreement between owner and architect by reference.
$8.00
C727-1992, Standard Form of Agreement Between Architect and Consultant for Special Services
Standard agreement between architect and consultant for special services for use when other C Series documents are inappropriate. This document is for planning, feasibility and post-occupancy studies and services requiring specialized descriptions.
$5.00
C801-1993, Joint Venture Agreement for Professional Services
For use by two or more parties to provide for their mutual rights and obligations. The parties may be all architects, all engineers, a combination of architects and engineers, or another combination of professionals. The document provides a choice between two methods of joint venture operation. The "Division of Compensation" method assumes that services provided and the compensation received will be divided among the parties in the proportions agreed to at the outset of the project. Each party's profitability is then dependent on individual performance of pre-assigned tasks and is not directly tied to that of the other parties. The "Division of Profit and Loss" method is based on each party performing work and billing the joint venture at cost plus a nominal amount for overhead. The ultimate profit or loss of the joint venture is thus divided between the parties at completion of the project, based on their respective interests.
$5.00
A101/CMa-1992, Standard Form of Agreement Between Owner and Contractor-Stipulated Sum, Construction Manager-Adviser Edition
A101/CMa is a standard form of agreement between the owner and contractor for use on a project where the basis of payment is a stipulated sum (fixed price), and where, in addition to the contractor and the architect, a construction manager assists the owner in an advisory capacity during design and construction. Prepared for use with A201/CMa-1992, General Conditions of the Contract for Construction-Construction Manager-Adviser.
$3.50
A121/CMc-1991, Standard Form of Agreement Between Owner and Construction Manager where the Construction Manager is also the Constructor
A121/CMc is intended for use on projects where a construction manager, in addition to serving as adviser to the owner, assumes financial responsibility for construction of the project. The construction manager provides the owner with a guaranteed maximum price proposal, which the owner may accept, reject or negotiate. Upon the owner's acceptance of the proposal by execution of an amendment, the construction manager becomes contractually bound to provide labor and materials for the project. The document divides the construction manager's services into two phases: the preconstruction phase and the construction phase, portions of which may proceed concurrently in order to fast-track the process. A121/CMc is for use with A201-1997, General Conditions of the Contract for Construction, and B141-1997, Standard Form of Agreement Between Owner and Architect.
$5.00
A131/CMc-1991, Standard Form of Agreement Between Owner and Construction Manager where the Construction Manager is also the Constructor-Cost Plus a Fee with No Guarantee of Cost
A131/CMc is intended for use when the owner seeks a constructor who will take on the responsibility for providing the means and methods of construction. A131/CMc uses a control estimate to determine the cost of the work and employs the cost plus a fee method, wherein the owner can monitor cost through periodic review of the control estimate, which is revised as the project proceeds.
$5.00
A201/CMa-1992, General Conditions of the Contract for Construction, Construction Manager-Adviser Edition
A201/CMa is an adaptation of A201-1997 and has been developed for construction management projects where a construction manager has been added to the team. Under A201/CMa, the construction manager has the role of an independent adviser to the owner. Caution: It is vital that A201/CMa not be used in combination with documents where it is assumed that the construction manager takes on the role of constructor, gives the owner a guaranteed maximum price, or contracts directly with those who supply labor and materials for the project.
$7.50
A511/CMa-1993, Guide for Supplementary Conditions, Construction Manager/Adviser Edition
A511/CMa is a guide to model provisions for A201/CMa-1992. It should only be employedas should A201/CMaon projects where the construction manager is serving in the capacity of adviser to the owner (as represented by the CMa document designation), and not in situations where the construction manager is also the constructor (CMc document-based relationships).
$9.00
B141/CMa-1992, Standard Form of Agreement Between Owner and Architect, Construction Manager/Adviser Edition
B141/CMa is a standard form of agreement between owner and architect for use on projects where construction management services are to be provided under separate contract with the owner. It is coordinated with B801/CMa-1992, an owner-construction manager/adviser agreement where the construction manager is an independent, professional adviser to the owner throughout the course of the project. Both B141/CMa and B801/CMa are based on the premise that a separate construction contractor will also contract with the owner. The Owner-Contractor agreement is jointly administered by the architect and construction manager under A201/CMa-1992.
$3.50
B144/ARCH-CM-1993, Standard Form of Amendment to the Agreement Between Owner and Architect where the Architect Provides Construction Management Services as an Adviser to the Owner
This document is an amendment for use in circumstances where the architect agrees to provide the owner a package of construction management services to expand upon, blend with and supplement the architect's design and other construction administration services described in B141-1997.
$3.50 (minimum order of 5 copies)
B801/CMa-1992, Standard Form of Agreement Between Owner and Construction Manager Where the Construction Manager is not a Constructor
Standard form of agreement for use on projects where construction management services are assumed by a single entity separate and independent from the architect and contractor, and who acts solely as an adviser (CMa) to the owner throughout the course of the project. Coordinated for use with B141/CMa-1992, both being based on the premise that there will be a separate, and possibly multiple construction contractor(s) whose contracts with the owner are jointly administered by the architect and construction manager under A201/CMa. Caution: B801/CMa is not coordinated with, and should not be used with, documents where the construction manager acts as the constructor (i.e., contractor) for the project.
$3.50
G701/CMa-1992, Change Order, Construction Manager-Adviser Edition
G701/Cma is essentially the same as G701, the major difference being that the signatures of the construction manager-adviser, owner, architect and contractor are required to validate the change order.
$18.00 50-pack
G702/CMa-1992, Application and Certificate for Payment, Construction Manager-Adviser Edition and G703, Continuation Sheet for G702
Though the purpose of G702/CMa is substantially similar to that of G702, the construction manager-adviser edition expands responsibility for certification of payment to include both the architect and construction manager. Both the architect and construction manager may certify a different amount than that applied for, with each initialing the figures that have been changed and providing written explanation(s) accordingly. The standard G703 is appropriate for use with G702/CMa.
$18.00 50-pack
G704/CMa-1992, Certificate of Substantial Completion, Construction Manager-Adviser Edition
Though the use and purpose of G704/CMa remains substantially similar to that of G704, the construction manager-adviser edition expands responsibility for certification of substantial completion to include both architect and construction manager. The contractor prepares a list of items to be completed or corrected, and the architect and construction manager verify and amend this list accordingly. If both parties find that the work is substantially complete, the form is prepared for acceptance by the contractor and owner.
$18.00 50-pack
G714/CMa-1992, Construction Change Directive, Construction Manager-Adviser Edition
G714/CMa is designed to effect the same type of substantive changes in the work described in the synopses of G714. The difference between the two lies not in purpose, but in execution: whereas the owner and architect must both sign the G714 in order for the directive to become a valid contractual instrument, G714/CMa requires execution by the owner, architect and construction manager-adviser.
$18.00 50-pack
G722/CMa-1992, Project Application and Project Certificate for Payment, Construction Manager-Adviser Edition and G723, Project Application Summary, Construction Manager-Adviser Edition
These documents are for use on construction management projects where the CM serves as an adviser to the owner. Each contractor submits separate G702/CMa and G703 documents to the construction manager-adviser, who collects and compiles them to complete G723/CMa. G723/CMa then serves as a summary of the contractors' applications, with project totals being transferred to G722/CMa. The construction manager-adviser can then sign the form, have it notarized and submit it along with G723/CMa (which has all of the separate contractors' G702/CMa forms attached) to the architect for review and appropriate action.
$18.00 50-pack
D101-1995, Architectural Area and Volume of Buildings
Establishes definitions for and describes methods of calculating the architectural area and volume of buildings. This document also covers interstitial space, office, retail and residential areas.
$9.00
D200-1995, Project Checklist
The project checklist is a convenient listing of tasks a practitioner may perform on a given project. This checklist will assist the architect in recognizing required tasks and in locating the data necessary to fulfill assigned responsibilities. By providing space for notes on actions taken, assignment of tasks and time frames for completion, this document may also serve as a permanent record of the owner's, contractor's and architect's actions and decisions.
$9.00
A191-1996, Standard Form of Agreement Between Owner and Design/Builder
Two agreements for use in sequence by an owner contracting with one entity serving as a single point of responsibility for both design and construction services. The first covers preliminary design and budgeting services, while the second deals with final design and construction. Although it is anticipated that an owner and a design/builder entering into the first agreement will later enter into the second, the parties are not obligated to do so and may conclude their relationship after the terms of the first agreement have been fulfilled.
$5.00
A491-1996, Standard Form of Agreement Between Design/Builder and Contractor
Two agreements for use in sequence by a design/builder and a construction contractor. The first agreement covers management consulting services to be provided during the preliminary design and budgeting phase of the project, while the second covers construction. It is presumed that the design/builder has contracted with an owner to provide design and construction services under the agreements contained in A191-1996.
$5.00
B901-1996, Standard Form of Agreement Between Design/Builder and Architect
Two agreements for use in sequence by a design/builder and an architect, the first covering preliminary design and the second covering final design. It is presumed that the design/builder has previously contracted with an owner to provide design and construction services under the agreements contained in A191-1996.
$5.00
G601-1994, Request for ProposalLand Survey
G601 allows owners to fine-tune a request for proposal from surveyors by checking appropriate boxes and filling in project specifics. The document may also form the agreement between owner and land surveyor once an understanding is reached.
$5.00
G602-1993, Request for ProposalGeotechnical Services
G602 is a request for proposal that, like G601-1994, can evolve to form the agreement between owner and geotechnical engineer. G602 allows the owner to tailor the proposal request to address specific project needs.
$5.00
G605-2000, Notification of Amendment to the Professional Services
G605 is intended for use by an architect when notifying an owner of a proposed amendment to most AIA owner-architect agreements.
$18.00 50-pack
G606-2000, Amendment to the Professional Services Agreement
This document is intended for use by an architect when amending the professional services provisions in most AIA owner-architect agreements.
$18.00 50-pack
G607-2000, Amendment to the Consultant Services Agreement
This document is intended for use by an architect or consultant when amending the professional services provisions in most AIA Architect-Consultant agreements, such as C141 and C142.
$18.00 50-pack
G607-2000, Amendment to the Consultant Services Agreement
This document is intended for use by an architect or consultant when amending the professional services provisions in most AIA Architect-Consultant agreements, such as C141 and C142.
$18.00 50-pack
G701-2000/2001, Change Order
G701 may be used as written documentation of changes in the work, contract sum or contract time that are mutually agreed to by the owner and contractor. G701 provides space for a complete description of the change and for the signatures of the owner, architect and contractor.
$18.00 50-pack
G702-1992, Application and Certificate for Payment and G703, Continuation Sheet
G702 and G703 provide convenient and complete forms with which the contractor can apply for payment and the architect can certify payment is due. The forms require the contractor to show the status of the contract sum to date, including the total dollar amount of the work completed and stored to date, the amount of retainage (if any), the total of previous payments, a summary of change orders and the amount of current payment requested. G703 breaks the contract sum into portions of the work in accordance with a schedule of values required by the general conditions. It serves as both the contractor's application and the architect's certification, and its use can expedite payment and reduce the possibility of error. If the application is properly completed and acceptable to the architect, the architect's signature certifies to the owner that a payment in the amount indicated is due to the contractor. The form also allows the architect to certify an amount different than the amount applied for when explanation is provided by the architect.
$18.00 50-pack or Continuous Roll
G704-2000, Certificate of Substantial Completion
G704 is a standard form for recording the date of substantial completion of the work or a designated portion thereof. The contractor prepares a list of items to be completed or corrected, and the architect verifies and amends this list. If the architect finds that the work is substantially complete, the form is prepared for acceptance by the contractor and owner. Appended thereto is the list of items to be completed or corrected. The form provides for agreement as to the time allowed for completion or correction of the items, the date when the owner will occupy the work or designated portion thereof, and a description of responsibilities for maintenance, heat, utilities and insurance.
$18.00 50-pack
G706A-1994, Contractor's Affidavit of Release of Liens
G706A supports G706-1994 in the event that the owner requires a sworn statement of the contractor stating that all releases or waivers of liens have been received. In such event, it is normal for the contractor to submit G706 and G706A, along with attached releases or waivers of liens for the contractor, all subcontractors and others who may have lien rights against the owner's property. The contractor is required to list any exceptions to the sworn statement provided in G706A and may be required to furnish to the owner a lien bond or indemnity bond to protect the owner with respect to such exceptions.
$18.00 50-pack
G706-1994, Contractor's Affidavit of Payment of Debts and Claims
The contractor submits this affidavit with the final request for payment, stating that all payrolls, bills for materials and equipment, and other indebtedness connected with the work for which the owner might be responsible have been paid or otherwise satisfied. G706 requires the contractor to list any indebtedness or known claims in connection with the construction contract that have not been paid or otherwise satisfied. The contractor may also be required to furnish a lien bond or indemnity bond to protect the owner with respect to each exception.
$18.00 50-pack
G707A-1994, Consent of Surety to Reduction in or Partial Release of Retainage
G707A is for use when a surety company is involved and the owner-contractor agreement contains a clause whereby retainage is reduced during the course of the construction project. When duly executed, the form assures the owner that such reduction or partial release of retainage does not relieve the surety of its obligations.
$18.00 50-pack
G707-1994, Consent of Surety to Final Payment
With G707, the owner may preserve its rights under bonds by obtaining the surety's approval of final payment to the contractor and its agreement that final payment will not relieve the surety of any of its obligations.
$18.00 50-pack
G709-2001, Proposal Request
G709 is used to obtain price quotations required in the negotiation of change orders. It is not a change order or a direction to proceed with the work; it is simply a request to the contractor for information related to a proposed change in the construction contract.
$18.00 50-pack
G710-1992, Architect's Supplemental Instructions
G710 is used by the architect to issue additional instructions or interpretations or to order minor changes in the work. The form is intended to assist the architect in performing obligations as interpreter of the contract document requirements in accordance with the owner-architect agreement and the general conditions. This form should not be used to change the contract sum or contract time. If the contractor believes that a change in the contract sum or contract time is involved, other G-Series documents must be used.
$18.00 50-pack
G711-1972, Architect's Field Report
G711 is a standard form for the architect's project representative to use in maintaining a concise record of site visits or, in the case of a full-time project representative, a daily log of construction activities.
$18.00 50-pack
G712-1972, Shop Drawing and Sample Record
G712 is a standard form by which the architect can schedule and monitor shop drawings and samples. Since this process tends to be complex, the schedule provided in G712 shows the progress of a submittal, which in turn contributes to the orderly processing of work. G712 can also serve as a permanent record of the chronology of the submittal process.
$18.00 50-pack
G714-2001, Construction Change Directive
G714 replaces former AIA Document G713, Construction Change Authorization. G714 was developed as a directive for changes in the work which, if not expeditiously implemented, might delay the project. In contrast to a change order, G714 is to be used where the owner and contractor, for whatever reason, have not reached agreement on proposed changes in the contract sum or contract time. Upon receipt of a completed G714, the contractor must promptly proceed with the change in the work described therein.
$18.00 50-pack
G715-1991, Instruction Sheet and Attachment for Acord Certificate of Insurance
G715 is intended for use in adopting ACORD Form 25-S to certify the coverage required of contractors under AIA Document A201-1997. The document consists of instructions for filling out the ACORD from and an attachment for information not called for on the ACORD form.
$18.00 50-pack
G804-2001, Register of Bid Documents
G804 serves as a log for bid documents while it is in the possession of contractors, subcontractors and suppliers during the bidding process. It is particularly useful as a single point of reference when parties interested in the project call for information during the bidding process.
$18.00 50-pack
G805-2001, List of Subcontractors
G805 is an administrative form intended for use in maintaining a list of proposed subcontractors to be employed by the contractor for various portions of any project.
$18.00 50-pack
G806-2001, Project Parameters Worksheet
G806 is an administrative form intended to help maintain a standard list of project parameters.
$18.00 50-pack
G807-2001, Project Team Directory
G807 keeps track of and provides a single point of reference for basic information about a project's owner, architect, contractor and other entities. It also serves as a checklist of information about the persons working on a project.
$18.00 50-pack
G808-2001, Project Data
G808 is for recording information project teams gather in the course of providing professional services. It should be completed piece by piece as a project progresses, and it should be periodically reviewed to ensure information relevance. The attached worksheet, G808A, Construction Classification Worksheet, can be used to supplement G808. It can help a design team work through the range of code compliance combinations available before choosing a final compliance strategy.
$3.00
G809-2001, Project Abstract
G809 establishes a brief, uniform description of project data to be used in the tabulation of architect marketing information and firm statistics. The intent is to provide a single-sheet summary where information can be sorted, compiled and summarized to present a firm's experience. Information compiled in G809 can support planning for future projects and answer questions pertaining to past work.
$18.00 50-pack
G810-2001, Transmittal Letter
G810 allows for the orderly flow of information between parties involved in the design and construction phase of a project. It serves as a written record of the exchange of project information and also acts as a checklist reminding the sender to tell the recipient how the material is being sent, why it is being sent and what exactly is being sent.
$18.00 50-pack
A171-1990, Standard Form of Agreement between Owner and ContractorStipulated Sum, for Furniture, Furnishings and Equipment (FF&E)
A171 is a standard form of agreement between owner and contractor for furniture, furnishings and equipment (FF&E) where the basis of payment is a stipulated sum (fixed price). A171 adopts by reference and is intended for use with AIA Document A271-1990, General Conditions of the Contract for Furniture, Furnishings and Equipment. It may be used in any arrangement between an owner and contractor where the cost of FF&E has been determined in advance, either through bidding or negotiation.
$3.50
A177-1990, Abbreviated Owner-Contractor Agreement for Furniture, Furnishings and Equipment (FF&E)
A177 is an abbreviated agreement philosophically deriving much of its content from the combination of A171-1990 and A271-1990. It is for use on projects where the contractor for furniture, furnishings and equipment (FF&E) has a prior working relationship with the owner, or where the project is relatively simple in detail or short in duration. Caution: This document is not intended for use on major construction work that may involve life safety systems or structural components.
$3.50
A271-1990, General Conditions of the Contract for Furniture, Furnishings and Equipment (FF&E)
When the scope of a contract is limited to furniture, furnishings and equipment (FF&E), A271 is intended for use in a manner similar to the way in which A201 is used for construction projects. Except for minor works, A271 should not be used for construction involving life safety systems or structural components.
$7.50
A571-1991, Guide for Interiors Supplementary Conditions
A571 is intended as an aid to practitioners in preparing supplementary conditions on interiors projects. It provides additional information to address local variations in project requirements where A271-1990 is used.
$9.00
A771-1990, Instructions to Interiors Bidders
For use on projects dealing with furniture, furnishings and equipment (FF&E). This document parallels A701-1997, but contains minor changes to maintain consistency with A271-1990 and its related FF&E documents.
$3.50
B171-1990, Standard Form of Agreement between Owner and Architect for Interior Design Services
B171 is intended for use when the architect agrees to provide an owner with design and administrative services for the procurement of interior furniture, furnishings and equipment (FF&E). B171 is coordinated with, and adopts by reference, A271. When B171 is used, it is anticipated that A271 will form part of the contract between the owner and contractor for FF&E.
$3.50
B177-1990, Abbreviated Form of Agreement for Interior Design Services
B177 is an abbreviated document similar to B171-1990, but with less complexity and detail. This document may be used where the owner and architect have a continuing relationship from previous work together or where the project is relatively simple in detail or short in duration.
$3.50
B611/INT-2002, Standard Form of Agreement Between Client and Consultant for use where the Project is located outside the United States
Designed to assist U.S. architects involved in projects based in foreign lands, where the U.S. architects are hired on a consulting basis for design services and local architects will be retained. This document is intended to clarify assumptions, roles, responsibilities and obligations of the parties; to provide a narrative description of services; and to facilitate, strengthen and maintain the working and contractual relationships between parties. This document also contains modular exhibits that may, at the discretion of the parties to the agreement, be used to further describe the circumstances of a relationship or a project.
$8.00
B621/INT-2002, Abbreviated Standard Form of Agreement Between Client and Consultant for use where the Project is located outside the United States
An abbreviated version of the B611/INT-2002, this document is most suitable for general international work of limited scope or on international projects with repeat clients. It does not contain the modularity of B611/INT-2002.
$8.00
Adobe Acrobat required to view PDF.
Click to download.
Sitemap
A I A Houston :: Home.
Partners
ripeoea.org
. The great
hotel kiev
with great suites.